4. (TCO C) A project to remodel a bathroom has the following activities. (Hint: You will need to build an AIB/AON diagram, perform a forward pass, and perform a backward pass to answer this question.)

ActivityDurationPredecessors

A2 months—

B4 months—

C4 months—

D1 monthA

E5 monthsB

F2 monthsB, C

G1 monthC

H3 monthsE, F, G

I2 monthsD, E

J2 monthsG, H

  1. What are the critical path activities? (5 points)
  2. What is the project’s scheduled completion time? (5 points)
  3. What is the slack or float for Activity A? Show your calculations. (5 points)
  4. What is the slack or float for Activity E? Show your calculations. (5 points)
  5. What is the slack or float for Activity F? Show your calculations. (5 points)
  6. What is the slack or float for Activity G? Show your calculations. (5 points)

(Points : 40)

Solution:

15% off for this assignment.

Our Prices Start at $11.99. As Our First Client, Use Coupon Code GET15 to claim 15% Discount This Month!!

Why US?

100% Confidentiality

Information about customers is confidential and never disclosed to third parties.

Timely Delivery

No missed deadlines – 97% of assignments are completed in time.

Original Writing

We complete all papers from scratch. You can get a plagiarism report.

Money Back

If you are convinced that our writer has not followed your requirements, feel free to ask for a refund.